§ 17.63.270. Procedure when construction falls behind schedule.  


Latest version.
  • The city council shall consider the planned unit development subject to revocation if construction falls more than two years behind the schedule filed with the final plat, or exceeds ten years. The developer shall be notified at least ninety days prior to any revocation hearing. Extensions of the building schedule agreed by the developer at the time of approval may be granted by the city council.

(Ord. 2995 § 2, 1995: (Ord. 1858 § 1 (Part), 1971: § 17(1.1.5)(B) of unnumbered Ord. dated 9/28/66)